Below is a timeline of the facility progress made during the Build Blue capital campaign. Renderings may not reflect the finished product.
October 2022 – February 2024 - Construction on new outdoor tennis facility
Gallery: Outdoor Tennis Facility Ribbon Cutting
For everyone that keeps inquiring… today is the day. #FacilityFriday pic.twitter.com/7LQTyXN70w
— The 4th Dimension (@MaplesLarryD) February 23, 2024
Gratitude Post: I am thankful for the opportunity to lead and be lead. The @MTAthletics Outdoor Tennis Complex is just a small example of what is to come. Thank you to each and every individual who made this vision a reality. This is #ThePriceOfProgress. #FacilityFriday pic.twitter.com/38Mj9s7lLQ
— The 4th Dimension (@MaplesLarryD) February 2, 2024
The new Outdoor Tennis Facility will take @MT_WomensTennis and @MT_MensTennis to new heights!#BLUEnited | #BuildBlue pic.twitter.com/epubKBO5Jo
— Middle Tennessee Athletics (@MTAthletics) February 2, 2024
We're cutting the ribbon on the brand new outdoor tennis facility tomorrow at 1 PM!
— Middle Tennessee Athletics (@MTAthletics) February 1, 2024
Join us there as we kick off a big weekend for @MT_WomensTennis and @MT_Menstennis. pic.twitter.com/5JYP6I8cUM
This week's #FacilityFriday features Court Cameras by @track_tennis and Artificial Turf by Goat Turf. Almost at the finish line. #Engaged pic.twitter.com/GnSIRhHjBZ
— The 4th Dimension (@MaplesLarryD) December 22, 2023
Sneak peak into The @MTAthletics Tennis Complex interior as we quickly approach substantial completion in a few weeks. #FacilityFriday pic.twitter.com/12dpWNrjQI
— The 4th Dimension (@MaplesLarryD) December 15, 2023
Ever wonder how we land on proper brick color? Study what we currently have with a vision for where we want to go. #Engaged pic.twitter.com/kzbrgkzrYx
— The 4th Dimension (@MaplesLarryD) December 11, 2023
Working with the team at John Thomas Designs has been nothing short of amazing. #FacilityFriday pic.twitter.com/STpQYjOdwo
— The 4th Dimension (@MaplesLarryD) December 8, 2023
Welcome to another #FacilityFriday featuring some of the finer details. Landscaping, Donor Chairbacks, Electrical Hookups. #Engaged pic.twitter.com/uzJK5hKmMA
— The 4th Dimension (@MaplesLarryD) December 1, 2023
Welcome to another #FacilityFriday at the @MTAthletics Tennis Complex as we pick some steam with the installation of @Daktronics scoreboards and the application of the court surfaces. #ThePriceOfProgress pic.twitter.com/myQf8jAdZi
— The 4th Dimension (@MaplesLarryD) October 27, 2023
Another #FacilityFriday closer to the completion of the @MTAthletics Outdoor Tennis Complex. pic.twitter.com/m4QHCZG708
— The 4th Dimension (@MaplesLarryD) October 20, 2023
Now that the @MTAthletics Tennis Complex fencing is up. We can now field verify and confirm our windscreen layout and design. #Engaged pic.twitter.com/i427vts0t0
— The 4th Dimension (@MaplesLarryD) October 7, 2023
Execution: ALL 8 post-tension (PT) concrete tennis courts have been poured and are curing. Courts set to get surfaced 28 days after last pour. #FacilityFriday pic.twitter.com/Kv24pl3j7Q
— The 4th Dimension (@MaplesLarryD) September 29, 2023
MTSU Tennis Complex #FacilityFriday pic.twitter.com/cP1gyMfVWU
— The 4th Dimension (@MaplesLarryD) August 18, 2023
Checking in on the beautiful MT Tennis Complex. #FacilityFriday pic.twitter.com/WOb9imyecU
— The 4th Dimension (@MaplesLarryD) July 14, 2023
#FacilityFriday pic.twitter.com/Mu4PmdvFFN
— The 4th Dimension (@MaplesLarryD) May 26, 2023
What being in the trenches really looks like. #FacilityFriday pic.twitter.com/KuLzgDjD2d
— The 4th Dimension (@MaplesLarryD) April 21, 2023
Tennis Complex support building starting to come to life. #FacilityFriday pic.twitter.com/EIfcvfeXYX
— The 4th Dimension (@MaplesLarryD) March 24, 2023
Quite a bit of progress for our New Outdoor Tennis Complex. #FacilityFriday pic.twitter.com/Egme2KI7A1
— The 4th Dimension (@MaplesLarryD) February 24, 2023
Gallery: Outdoor Tennis Facility Progress
Structural Steel Install in progress...
— The 4th Dimension (@MaplesLarryD) February 3, 2023
Duration - 35 Days#Engaged pic.twitter.com/YmLBR3IvLT
The Price of Progress for @MT_MensTennis and @MT_WomensTennis. #Engaged pic.twitter.com/y19rxOa3tj
— The 4th Dimension (@MaplesLarryD) February 9, 2023
February 28, 2023 - Architect field report on new outdoor tennis facility
January 26, 2023 - Groundbreaking ceremony for Student-Athlete Performance Center
Gallery: SAPC Groundbreaking
Gallery: SAPC Conceptual Renderings
September 15, 2022 - Groundbreaking ceremony for new outdoor tennis facility
Gallery: Tennis Facility Groundbreaking Ceremony
August 14, 2022 - Reveal of new Murphy Center basketball court design
It’s a special year for Murphy Center, and, in addition to new windows, we’re celebrating its 50th birthday with a new court design!
— MT Athletics (@MTAthletics) August 14, 2022
We can’t wait to have you back at the Glass House soon to watch @MT_WBB and @MT_MBB on the new floor! ?? pic.twitter.com/M5xAN9OEJE
July 1, 2022 - New trash and recycling receptacles in Murphy Center
Helping @bonifaceamuzu improve the guest experience and keep Blue Raider fans coming back to Murphy Center every year with the @MaxRbins prototypes. Before and After. Details Matter. #Engaged #FacilityFriday pic.twitter.com/3tcrMxKvBO
— The 4th Dimension (@MaplesLarryD) July 1, 2022
June 17, 2022 - Q&A with Associate AD Larry Maples
May 23, 2022 - Design meeting for on-campus tennis facility

Outdoor tennis facility design meeting topics discussed:
- Location of graphics on wind screens behind the baselines on the court
- MT primary logo behind four courts alternating
- Middle Tennessee wordmark behind the other four courts alternating
- Blue Raiders wordmark to be on the windscreens facing the courts on the west side of the facility
- Discussion regarding office/locker room building wall graphic designs
May 19, 2022 - Murphy Center glass replacement update
A little update on the Glass House ??
— MT Athletics (@MTAthletics) May 19, 2022
Old ?? New ?? pic.twitter.com/xFaKARcleB
Excerpt from Feb. 4, 2022 press release regarding the Murphy Center glass replacement:
The University, as part of the Build Blue campaign, is replacing all of the antiquated glass with a more modern system. The new Sage Glass system will offer a better appearance while providing automatic dimming for glare control. It will allow the benefits of natural light without aesthetic limitations of blinds, shades or curtains.
May 17, 2022 - Student Athlete Performance Center design meeting

Student Athlete Performance Center design meeting topics discussed:
- This is the fourth and final design development phase meeting
- Premium level floor plan review (level 3 of SAPC)
- Seating counts: interior – 236; exterior – 64; total – 300
- Capacity: stadium events – 480; cocktail receptions – 450
- All-team room projector screen study
- All-team room aisle study
May 16, 2022 - Sports Medicine space design meeting for Student Athlete Performance Center

Sports Medicine SAPC design meeting topics discussed:
- Treatment tables and attached containers/cabinets
- Location of internet/data on the treatment table island
- Storage for cases/trunks and shelving
- X-ray and exam rooms
- Ice room
- Weight/rehab area
May 9, 2022 - Student Athlete Performance Center design meeting and site surveys

Student Athlete Performance Center design meeting topics discussed:
- Equipment lab
- Office area (bullpen, hallways, reception/waiting areas, mail/copy room)
- Head Coach’s office
- All-staff meeting room
- Defensive meeting room
- Position group meeting room example
- All-team meeting room (seating/aisle options, location of screen(s), ceiling color, whiteboard type)
- Terrace
- Hospitality suite
We’ve got some core drilling going on this week as part of the site surveys required to BUILD BLUE. #Engaged pic.twitter.com/Iee8JLaroz
— The 4th Dimension (@MaplesLarryD) May 9, 2022
April 27, 2022 - Design meeting for new on-campus tennis facility
On-campus tennis facility design meeting topics discussed:
- Color of tennis courts
- Color of metal to go on the building that houses offices and locker rooms
- Locker room layout
- VIP viewing area
- Wi-Fi extension to courts and viewing areas
- Position of security cameras
- Court lighting options
Details, details, and even more details. Trust and believe the work is being done and we can’t to share more. #Engaged pic.twitter.com/RYULaUXmwT
— The 4th Dimension (@MaplesLarryD) April 27, 2022
April 25, 2022 - Information released regarding Steve Peterson Champions Plaza
March 18, 2022 - Student Athlete Performance Center design development phase begins
What does the Design Development Phase look like?
— The 4th Dimension (@MaplesLarryD) March 18, 2022
Starting with a baseline and customizing to fit the Middle Tennessee Vision. #BuildBlueNow pic.twitter.com/yWS3nXNIst
March 18, 2022 - Renderings of new on-campus tennis facility provided by WBA Architecture
Let's pop off another #FacilityFriday with some more details for @MT_MensTennis and @MT_WomensTennis on campus facility provided by @wbaarchitecture. #Engaged #BuildBlueNow pic.twitter.com/k8nwFYW3iS
— The 4th Dimension (@MaplesLarryD) March 18, 2022
March 17, 2022 - Meeting to design Student Athlete Performance Center weight room
@Coach_Hick_ in his element working on SAPC Weight Room. #BuildBlueNow pic.twitter.com/VQT6UxLpsa
— The 4th Dimension (@MaplesLarryD) March 17, 2022
March 11, 2022 - Student Athlete Performance Center schematic phase complete
Facility Friday...
— The 4th Dimension (@MaplesLarryD) March 11, 2022
We are 100% done with Schematic Design Phase.
On to Design Development.#BuildBlueNow #Engaged pic.twitter.com/8idcfUNb21
Schematic Design Phase of the new facility? 100% finished. Design Development up next ??. #FacilityFriday #BuildBlueNow | #BLUE23ASON pic.twitter.com/qtLBqFONBr
— Middle Tennessee Football Recruiting (@MTFB_Recruiting) March 11, 2022
March 2, 2022 - Student Athlete Performance Center design meeting with football staff and athletic training staff
HUGE Work Day as we dive into the future of @MTAthletics Student Athlete Performance Center. #BuildBlue #Engaged pic.twitter.com/2bCl2xewGP
— The 4th Dimension (@MaplesLarryD) March 2, 2022
February 26, 2022 - $1.5 million gift by John Floyd of Ole South Homes announced
Thank you to John Floyd of Ole South Homes for your transformational gift of $1.5 million to the Build Blue campaign, announced during @MT_MBB game tonight! #BuildBlue @MTAthletics @ChrisMassaroAD @ldeleon5 @OleSouthHomes pic.twitter.com/2ckZa0ENKP
— Sidney A. McPhee (@PresidentMcPhee) February 27, 2022
February 9, 2022 - Design meeting for new on-campus tennis facility
Details matter when working on @MT_MensTennis @MT_WomensTennis on campus facility. #Engaged pic.twitter.com/wL2Sq2T50k
— The 4th Dimension (@MaplesLarryD) February 9, 2022
February 8, 2022 - Murphy Center window replacement begins
The first truck carrying the curtain wall glass has arrived at MurphyCenter. Let the glass replacement begin! #buildbluenow pic.twitter.com/W475K2MztM
— Chris Massaro (@ChrisMassaroAD) February 8, 2022
February 4, 2022 - Murphy Center glass replacement announcement
January 21, 2022 - Nashville Ledger article
January 1, 2022 - Q&A with AD Chris Massaro
Phase One is financed and we're meeting with architects, and hopefully we can put their plans to contractors sometime early summer for our Student Athlete Performance Center, which will help every sport we have.Director of Athletics Chris Massaro
We still have a lot of fundraising to do (for Phase Two and Three), but we've had tremendous fundraising success this fall, and we're looking forward to the first quarter of next year of also having a lot of fundraising success.
December 15, 2021 - Design meetings for the new on-campus tennis facility and the Student Athlete Performance Center
Jumping on a Zoom Call with @CoachJimmyB @MT_MensTennis @MT_WomensTennis from The Bahamas to work on the NEW Tennis Facility. #Engaged pic.twitter.com/PItuT7FwAc
— The 4th Dimension (@MaplesLarryD) December 15, 2021
Jumping from 1 call to another. Student Athlete Performance Center in the works. #Engaged pic.twitter.com/E4wu7cDWK6
— The 4th Dimension (@MaplesLarryD) December 15, 2021
December 2, 2021 - Student Athlete Performance Center design meeting
The Student Athlete Performance Center Programming Session with the current and former athletes. #Engaged pic.twitter.com/q8eE6hBkKh
— The 4th Dimension (@MaplesLarryD) December 2, 2021
November 17, 2021 - Announcement of SAPC design firms
Design of the Student Athlete Performance Center is done by GMC+HOK.
Goodwyn Mills Cawood (GMC) is one of the largest architecture and engineering firms in the Southeast, with offices located throughout Alabama, Florida, Georgia, Louisiana, South Carolina and Tennessee.
HOK is a global design, architecture, engineering and planning firm with 1,600 people collaborating across a network of 24 offices on three continents.
GMC and @HOKNetwork were chosen by @MTSU to design the new @MTAthletics Student-Athlete Performance Center, the first of a three-phase, $100-million-plus plan to enhance the school’s athletic facilities. Learn more: https://t.co/UH4csy3Vau #buildingcommunities #BuildBlueNow pic.twitter.com/Z8U8BkHcf0
— Goodwyn Mills Cawood (@goodwynmills) November 23, 2021
November 15, 2021 - Build Blue campaign announcement
Gallery: Build Blue Now
Phase one is a go. Phase two is important to our University and the surrounding region, and that's what we're raising money for now. Let's roll up our sleeves, and we've still got work to do.Director of Athletics Chris Massaro
Today has changed the landscape of Blue Raider Athletics for decades to come.#BuildBlueNow pic.twitter.com/sK11f4UMWN
— MT Athletics (@MTAthletics) November 16, 2021